1) WBS dictionary alone is given as input to ________________
2) Scope baseline documents WBS, WBS dictionary, project scope statement are updated in _____________ process
3) Final product,service or result is produced as an output of _____________ process
4) Approved change requests are implemented in ______________ process
5) Planning component is a tool used in _________________ process
6) Dependency among activities are determined during ________________ process
7) Resource breakdown structure is an output of ________________ process
8) What-if scenario analysis is a tool used in __________________ process
9) Advertising is a tool used in ___________________ process
10) Procurement audit is a tool used in __________________ process
11) Proposal evaluation technique is a tool used in ___________
12) Contract management plan is an input to _______________
13) Quality audit is a tool used in ________________ process
14) Cost of quality (COQ) is a tool used in _____________ process
15) Perform quality control produces validated _______________ and validated ________________
16) Risk management planning uses the tools __________________
17) ______________ is the output of risk identification process that is updated throughout the processes in risk management knowledge area
18) Co-location is a tool used in _________________
19) Issue log is a tool used in ________________ and _________________
20) ___________________ and __________________ reporting systems are used as tools in performance reporting
21) Funding limit reconciliation is a tool used in __________________
22) Cost change control system is a tool used in __________________
23) Contract is given as an input to ___________________
24) Best form of conflict resolution is _________________
25) _____________ theory has a positive attitude towards employee performance
26) The lowest level of need in Maslows theory is ____________
27) The highest level of need in maslow's theory is __________
28) Various stages in team development are ______________,___________,_______________,_______________,___________
29) RACI chart is a form of ____________
30) ___________ is a component of staffing management plan that determines the work that needs to be done in graphical format
31) All work and effort performed within a control account is documented in a ________________
Answers :
1) Scope verification
2) Scope control
3) Close project
4) direct and manage project execution
5) activity definition
6) activity sequencing
7) activity resource estimating
8) schedule development
9) request seller responses
10) contract closure
11) select sellers
12) contract administration
13) perform quality assurance
14) quality planning
15) defect repair, deliverables
16) planning meeting and analysis
17) risk register
18) develop project team
19) manage project team, manage stake holders
20) time reporting system, cost reporting system
21) cost budgeting
22) cost control
23) contract administration, develop project charter
24) confronting (or) problem solving
25) Theory Y
26) physiological
27) self-actualization
28) forming,storming,norming,performing,disjourning/adjoining
29) RAM (responsibility assignment matrix)
30) resource histogram
31) control account plan